Guide · SCHEDULE REVIEW

Project schedule review checklist: 12 checks before a meeting

To review a project schedule, check that every task is linked to its predecessors and successors, that dates and durations are plausible, that milestones are real, that resources are not double-booked, and that the finish date matches the commitment. You can do all of it read-only, without editing the plan.

Get GanttPeek on the App Store

Published by Eutopix Labs P.S.A., the developer of GanttPeek. Microsoft Project is a trademark of Microsoft; GanttPeek is independent.

Before you start

Reviewing is not planning. You are reading someone else’s schedule to find questions, not to change it. Open a copy, note the file name and date, and keep the original untouched. That is exactly the case for a read-only viewer: GanttPeek opens an MPP, Project XML, Primavera XER or MPX file without writing to it.

The twelve checks

  1. Scope: does the outline match the scope you were promised, with no missing phase?
  2. Links: does every task except the first and last have a predecessor and a successor? Open ends hide delays.
  3. Dependency types: are start-to-start and finish-to-finish links and lags used on purpose, and explained?
  4. Durations: are there very long tasks that should be split, or suspiciously short ones for heavy work?
  5. Dates: are tasks pinned to fixed dates or constraints that block the logic from driving the plan? Where constraints are not extracted, ask the planner.
  6. Milestones: are they zero-duration, linked to real deliverables, and do the key ones have a date you can quote?
  7. Resources: is anyone named on overlapping tasks, and are the right trades or people assigned?
  8. Calendars: do working days, holidays and shifts match how the work will actually run?
  9. Progress: does percent complete agree with what you saw on site, in the sprint or in the last report?
  10. Critical path: which chain sets the finish, and how much float do the near-critical chains have?
  11. Finish date: does it match the contract, launch or customer commitment?
  12. Revision: what changed since the last version, and who agreed to it?

Doing the checks read-only

CheckIn GanttPeek
Scope and hierarchyTask table with the outline, search and sort.
LinksInspector shows predecessors and successors; related tasks are one tap away.
Dates and durationsStart, finish and duration columns; the Gantt timeline for overlaps.
MilestonesMilestone filter.
ResourcesResource names and basic assignments, where the file carries them.
Progress and baselinesShown where the file provides them; unavailable fields are labelled.
Revision changesCompare revisions: changed, added and removed tasks with before and after dates.
Notes for the meetingProject notebook for meeting notes and action items beside the schedule.

Compare revisions is a read-only comparison, not a recalculated critical path.

What a viewer cannot tell you

  • Whether the schedule logic is sound. A viewer shows the links that exist; it does not rebuild the schedule.
  • Anything in fields that are not extracted, which for MPP files today include constraints, notes, calendar exceptions, custom fields and resource capacity and costs. Check the in-app data note.
  • Whether the plan is contractually correct. GanttPeek is not a certified scheduling or contractual-verification system.

Turning the review into actions

End with a short list: the question, who owns it, and a date. Export a PDF schedule report to attach to the minutes, or a CSV of the tasks you flagged. Then keep the notes beside the schedule so the next review starts from them. See the guide on keeping project review notes beside the schedule for how the notebook works.

Red flags that deserve a question

  • A long chain of tasks with no float and no buffer before a hard date.
  • Many tasks starting on the same day, which often means missing predecessors.
  • Milestones with no predecessors, which can be moved without anything noticing.
  • Percent complete that has not moved since the last revision.
  • A finish date that is exactly the contract date, with no margin.

None of these proves a problem. Each is a prompt for a question, and the answer belongs to the person who owns the plan.

Who should review, and when

A schedule gets better when someone other than its author reads it. Clients, owners’ representatives, subcontractors and project sponsors all read plans they did not build, often on a phone or tablet between other meetings. Review at every formal revision, before a progress meeting, and before any change that moves a key milestone. Put the same twelve checks in the same order each time so a reviewer can compare one revision with the next.

A ten-minute version for a phone

  1. Open the schedule and read the project finish date first.
  2. Filter to milestones and check each date against what you were promised.
  3. Scan the Gantt for tasks stacked on one start date.
  4. Open two or three tasks on the longest chain and read their predecessors.
  5. Write down the questions, with an owner for each, in the notes.

It will not replace a full review, but it is enough to arrive at a meeting with sharp questions instead of general ones.

Questions

What should a schedule review include?

Logic and links, durations, constraints, milestones, resources, calendars, progress, the critical path and the finish date against the commitment.

Can I review a schedule on an iPad?

Yes. GanttPeek opens supported schedule files on iPad through Apple’s document picker, offline and without uploading.

How often should I review a schedule?

At every formal revision and before each progress meeting is a sensible rhythm, adjusted to how fast the plan changes.

Does reviewing in GanttPeek change the file?

No. It is read-only and never writes to the source schedule.