Baseline, scheduled and actual are three different things
| Term | What it is | Does it change? |
|---|---|---|
| Baseline | The plan as approved. A frozen copy. | Only when someone deliberately re-baselines. |
| Scheduled (current) | The latest forecast: where the schedule says each task starts and finishes today. | Yes, with every update and every change to logic. |
| Actual | What really happened: the dates a task really started and finished. | Recorded once the work happens. |
Variance compares the scheduled (or actual) date with the baseline date. If a task was baselined to finish on 14 March and is now forecast to finish on 19 March, its finish variance is +5 days. A positive number is late; a negative number is early.
When a baseline is set
A baseline is usually saved once the plan is approved, before work starts. Setting it too early records a plan nobody agreed to; setting it too late hides the first slips. After that it should stay put. Planners may add a second baseline after a formal change, so the original and the revised plan can both be compared.
In Microsoft Project, the baseline is saved with the Set Baseline command, and the program can keep a primary baseline plus numbered baselines (Baseline 1 to Baseline 10). It also has interim plans, which save start and finish dates only. Primavera P6 handles baselines as separate saved copies of the project that you assign for comparison.
How to review baseline variance
- Ask which baseline you are looking at and when it was saved. “Baseline 0 from March” and “the re-baseline after the change order” tell different stories.
- Start with the milestones. Compare each key milestone with its baseline date.
- Look at the finish variance of the last task. That is the headline: how far the whole project has moved.
- Look for the tasks that slipped first. The earliest slip on a chain usually explains the later ones.
- List the tasks that finish later than baseline and are not yet complete. Those are the ones to ask about.
- Check whether the project was re-baselined. A schedule that was re-baselined recently can look on time while the original plan is far out of reach.
A small example
The figures below are invented to show the arithmetic. Read down the variance column and ask two questions: where did the slip start, and does it carry through to the end date?
| Task | Baseline finish | Current finish | Finish variance | Status |
|---|---|---|---|---|
| Foundations | 10 Mar | 10 Mar | 0 days | Complete |
| Frame | 24 Mar | 31 Mar | +7 days | Complete, finished a week late |
| Services first fix | 07 Apr | 16 Apr | +9 days | In progress |
| Handover | 12 May | 21 May | +9 days | Not started |
The pattern is more useful than any single number. Frame finished a week late, services lost two more days, and handover moves by the same nine days. That points to the frame as the first cause, and it shows the end date is already nine days past the approved plan.
Common baseline mistakes
- No baseline at all. Without one you can say a task is late only against someone’s memory.
- Re-baselining to make the variance disappear. The slip is real; the new baseline only hides it.
- Reading variance on completed tasks as a warning. A finished task with +3 days is history, not a forecast.
- Comparing bars at different time scales. Compare dates, not bar lengths.
Where GanttPeek helps, and where it does not
GanttPeek is a read-only viewer for schedule files on Mac, iPhone and iPad. Whether baseline dates come through depends on the file and its format; the app’s data note tells you what a particular file carried, and a Project XML export from the sender is the format the app itself suggests when fields are missing.
When the file has baseline dates, GanttPeek draws the baseline as a thin bar under each task bar, shows the finish variance in days, offers a “Late vs baseline” filter and adds baseline columns to the CSV export. When no task has a baseline, those controls stay hidden rather than showing empty values.
Limits to know: it compares against the primary baseline only (Baseline 0, or the lowest-numbered dated baseline), not against Baseline 1 to 10, and interim plans are not treated as baselines. It does not set or change baselines, and it does not recalculate the schedule.
To compare a new revision of a schedule against one you already reviewed, GanttPeek can also compare two files and list changed, added and removed tasks with their before and after dates.
Questions
What is a baseline in project management?
A baseline is the approved plan saved as a snapshot, so progress and changes can be measured against it.
What is the difference between baseline and actual?
The baseline is what you planned. Actual is what happened. The scheduled or current dates are the latest forecast between the two.
What is baseline variance?
The difference between a task’s current date and its baseline date, usually in days. Positive means later than planned.
Can GanttPeek show baselines from an MPP file?
GanttPeek shows baseline bars and variance when the opened file carries baseline dates. If the file does not, the controls stay hidden and the data note says what was not available.