The two definitions side by side
Both numbers measure spare time, but they protect different things. Total float protects the end date of the project (or a deadline set on the schedule). Free float protects the next task.
| Total float | Free float | |
|---|---|---|
| Question it answers | How late can this task finish before the project finish moves? | How late can this task finish before a successor has to start later? |
| Calculated as | Latest finish minus earliest finish (or latest start minus earliest start) | Earliest start of the next task minus this task’s earliest finish |
| Shared with other tasks? | Yes. Tasks in the same chain draw on the same float. | No. It belongs to this task alone. |
| Name in Microsoft Project | Total Slack | Free Slack |
| Name in Primavera P6 | Total Float | Free Float |
The ordering is fixed: 0 ≤ free float ≤ total float for any task with a normal finish-to-start link. If a task has zero total float, it is critical, and its free float is zero too.
A worked example
Six tasks, durations in working days, day 0 is the start. A is first. B1 and B2 run one after the other on one branch, C runs on a second branch, and D needs both branches. E is the handover.
| Task | Days | Needs first | Earliest start | Earliest finish | Latest finish | Total float | Free float |
|---|---|---|---|---|---|---|---|
| A | 3 | none | 0 | 3 | 3 | 0 | 0 |
| B1 | 2 | A | 3 | 5 | 6 | 1 | 0 |
| B2 | 2 | B1 | 5 | 7 | 8 | 1 | 1 |
| C | 5 | A | 3 | 8 | 8 | 0 | 0 |
| D | 4 | B2 and C | 8 | 12 | 12 | 0 | 0 |
| E | 1 | D | 12 | 13 | 13 | 0 | 0 |
The project takes 13 days, because A, C, D, E is the longest chain (3 + 5 + 4 + 1). The B branch takes 3 + 2 + 2 + 4 + 1 = 12 days, so it has one day of total float. That one day belongs to the whole branch, not to each task on it.
B1 has total float of 1 but free float of 0. If B1 slips by one day, B2 has to start a day later. The project still finishes on day 13, but B2 has now used the float and the branch is critical. B2 has free float of 1 because D cannot start before day 8 anyway.
How to calculate each one
- Do a forward pass to get every task’s earliest start and earliest finish. The last earliest finish is the project duration.
- Do a backward pass from the end date to get every task’s latest start and latest finish.
- Total float = latest finish minus earliest finish.
- Free float = the smallest earliest start among the successors, minus this task’s earliest finish. For a task with several successors, use the earliest of them.
- A task with no successor has free float equal to its total float.
Negative float
Float can go below zero. Negative total float means the schedule logic puts the finish after a date it is supposed to meet, for example a contract completion date entered as a constraint. A task with -3 days of float must be shortened, overlapped or re-sequenced by three days to hit that date.
Negative float usually points to a deadline or constraint, not to a calculation error. When you see it in a schedule you were sent, ask which constraint or deadline produces it.
Why the difference matters in a review
- Total float tells you how much room the whole chain has. Free float tells you how much one task can slip without disturbing the next person.
- A chain with one or two days of total float behaves almost like the critical path. One slip and it is critical.
- Lots of zero free float with positive total float means the tasks are tightly chained: only the chain as a whole has spare time.
- Whose float it is, the contractor’s, the client’s or nobody’s, is a contract question, not a scheduling one. Check the contract before you use the number in a dispute.
What changes the numbers
- Constraints such as “must start on” or “finish no later than” override the logic and change float.
- Calendars: float is counted in working time, so weekends, holidays and shifts change it.
- Lags and leads on links, and link types other than finish-to-start.
- Missing links. A task with no successor shows float it may not really have. Check the logic first.
Where GanttPeek helps, and where it does not
GanttPeek is a read-only viewer for Microsoft Project, Primavera P6 and MPX schedule files on Mac, iPhone and iPad. It does not show a total float or free float column, and it does not calculate float or recalculate a schedule. Do not use it to produce float numbers.
What it does give you is the material to question the numbers. The task list and Gantt timeline show dates, durations and the dependency arrows, so you can follow a chain by eye and see which branch finishes last. Where the source file marks tasks as critical, GanttPeek shows that flag; where it does not, the app says critical-path flags were not extracted from the file instead of guessing.
If float matters for a decision, ask the planner to export the schedule table with the Total Slack and Free Slack columns (or Total Float and Free Float in P6) to PDF or a spreadsheet, and read it next to the Gantt chart in GanttPeek.
Questions
What is the difference between total float and free float?
Total float is the delay a task can absorb before the project finish moves. Free float is the delay it can absorb before the next task has to start later. Free float is never larger than total float.
Can float be negative?
Yes. Negative total float means the logic finishes later than a required date, usually a constraint or a contract completion date.
Is float the same as slack?
In practice yes. Microsoft Project calls them Total Slack and Free Slack; Primavera P6 calls them Total Float and Free Float.
Does GanttPeek show float?
No. GanttPeek shows dates, durations, dependencies and critical flags where the file carries them, but it does not show or calculate float.