How to read a Gantt chart: bars, arrows, milestones and baselines

A Gantt chart lists tasks down the left and shows time across the top. Each bar starts when its task starts and ends when it finishes, so a longer bar is a longer task. Arrows show which task must finish before another can start, diamonds are milestones, and a shaded part of a bar shows progress.

Get GanttPeek on the App Store

Published by Eutopix Labs P.S.A., the developer of GanttPeek. Microsoft Project is a trademark of Microsoft; GanttPeek is independent.

The symbols you will meet

What you seeWhat it means
Horizontal barOne task. Left edge is the start, right edge is the finish, length is the duration.
Bracket-shaped or thick bar over a groupA summary task. It spans everything inside the group and has no work of its own.
DiamondA milestone: a point in time with zero duration, such as “Handover”.
Arrow between barsA dependency. The most common type, finish-to-start, means the second task cannot start until the first finishes.
Darker part of a barProgress: the share of the task reported as done.
Vertical lineA status date or today line. Bars left of it should be complete.
Thin bar under a task barThe baseline: where the task was planned to be when the plan was approved.
Red or highlighted barOften a critical task, one with no float. The colour is a choice the software or the planner makes, so check the legend.

Seven steps to read one

  1. Read the time scale first. Check whether the columns are days, weeks or months. A bar looks short or long depending on zoom, so compare lengths only at one scale.
  2. Find the end. The right edge of the last bar or the final milestone is the planned finish. Then find the start so you know the overall span.
  3. Read the summary bars. Phases such as Design, Build and Handover give you the shape of the project before you look at any detail. Look at how much they overlap.
  4. Follow the arrows. Pick a task you care about and trace what comes before and after it. A task with no arrows in or out is suspect: it may be missing a link, and then a delay in it will not move anything on the chart.
  5. Look at the milestones. They are the dates people commit to. Check which tasks lead into each one.
  6. Compare progress with the status date. Any bar to the left of the status line that is not fully shaded is behind.
  7. If baselines are shown, compare each bar with its baseline. The gap is the variance: how far the task has moved since the plan was approved.

A short example

Say a chart shows three summary bars: Design (weeks 1 to 4), Build (weeks 3 to 10) and Handover (weeks 10 to 11), with a diamond at the end of week 11 labelled “Go live”. Design and Build overlap in weeks 3 and 4, so some building starts before design is finished. That is allowed, but it carries risk if design changes.

Now open Build. One task, “Install frame”, has an arrow into “Fit-out” and nothing else. If “Install frame” slips two weeks, you can see that Fit-out moves and, behind it, Handover and Go live. If a task in Build had no arrows at all, a two week slip would change nothing on the chart, and that is the moment to ask whether a link is missing.

Mistakes beginners make

  • Reading the chart as a to-do list. The order of rows is the outline, not the order of work.
  • Assuming a long bar is a big task. It may be a small amount of work spread over a long time.
  • Ignoring weekends and holidays. Many charts skip non-working days, so a bar that crosses a weekend can look shorter than its calendar span.
  • Trusting colours without a legend. The same colour can mean critical in one file and a resource group in another.
  • Forgetting the zoom. A chart zoomed out to months hides short tasks that matter.

Reading the table beside the chart

Most Gantt charts sit next to a table. The usual columns are task name, start, finish, duration, predecessors and percent complete. Use the table for exact dates and the chart for patterns.

The outline numbers (1, 1.1, 1.2, 2…) show the hierarchy. Indented tasks belong to the summary task above them. When a summary is collapsed you only see its overall span.

What a Gantt chart cannot tell you

  • Whether the logic is right. A chart shows the links that exist, not the ones that should.
  • How much spare time a task has. For that you need float, or the critical path calculated by the planning software.
  • Effort and cost. Bar length is elapsed time, not work.
  • Whether the dates are realistic. A neat chart can sit on optimistic durations.

Reading a Microsoft Project Gantt chart on a Mac or iPad

Microsoft Project does not run on macOS, iOS or iPadOS, so a schedule sent to you as an .mpp file will not open by double-clicking. GanttPeek is an Apple-platform viewer that reads it on your device with no upload.

Its Gantt view follows the conventions above. It draws tasks, summary bars and milestones differently, shows dependency arrows that you can switch off, and has a legend for Task, Critical, Complete, Status date and Baseline. Critical appears only when the file carries critical-path flags, and the baseline ghost bar appears only when the file has baseline dates. “Fit Project” zooms the timeline to the whole schedule. You can export the chart as a multi-page PDF or a PNG image.

GanttPeek is read-only. It shows what the file contains. It does not reschedule tasks or fix missing links.

Questions

How do you read a Gantt chart for beginners?

Read the time scale, find the start and finish, read the summary bars for the phases, then trace the arrows between tasks. Diamonds are milestones and a shaded part of a bar is progress.

What do the arrows on a Gantt chart mean?

They are dependencies. An arrow from the end of one bar to the start of another means the second task cannot start until the first has finished.

What does a diamond mean on a Gantt chart?

A milestone: a point in time with no duration, such as an approval or a handover.

Can I read a Microsoft Project Gantt chart on an iPad?

Yes, with a viewer that reads MPP files, such as GanttPeek. It shows the task list and Gantt timeline read-only on iPhone, iPad and Mac.